Design Consultant Main Contractor Contractual Completion Date
Autor: ahmed_ep • April 29, 2015 • Essay • 596 Words (3 Pages) • 937 Views
Project Manager | RW Armstrong |
Design Consultant | EWAN |
Main Contractor | Consolidated Contracting Engineering & Procurement SAL-Offshore |
Contractual Completion Date | No. of Days Left for Completion |
Weather | ▢ Dusty ▢ Sunny ▢ Cloudy/Shower [pic 6] | Humidity | ▢ High ▢ Medium ▢ Low [pic 7] |
Temperature 0C |
| Max | 30 | Min | 20 |
Contractor's Manpower | Subcontractor's Manpower | |||||||
Category | Day Shift | Night Shift | Category | Day Shift | Night Shift | Name | Indirect | Direct |
Sr. PROJECT MANAGER | 1 | 0 | ||||||
PROJECT MANAGER | 1 | 0 | ||||||
MECH-ENGINEER | 1 | 0 | ||||||
ELEC-ENGINEER | 1 | 0 | ||||||
QA/QC Engr. | 1 | 0 | ||||||
MEP DRAUGHTS MAN | 6 | 0 | ||||||
SECRETARY | 1 | 0 | ||||||
ELECTRICAL FOREMAN | 1 | 0 | ||||||
PLUMBING FOREMAN | 2 | 0 | ||||||
Electricians | 4 | 0 |
| |||||
Plumbers | 14 | 0 |
|
|
| |||
Duct Man | 0 | 0 |
|
|
| |||
CHW.Pipe Fitter | 0 | 0 |
|
|
| |||
Storekeeper | 1 | 0 |
|
|
| |||
Safety Officer | 1 | 0 |
|
|
| |||
Fire Fighting | 0 | 0 |
|
|
| |||
Time Keeper | 0 | 0 |
|
|
| |||
Mech-Helper | 05 | 0 |
|
|
| |||
Elec-Helper | 05 | 0 |
|
|
| |||
|
|
| ||||||
|
|
| ||||||
TOTAL | 45 | 00 | TOTAL |
The contents of this report are a description of items related to the ongoing works or works completed during the day and indicative for the material & manpower on site, and should not in any case be considered a reference document for any contractual implication. |
EQUIPMENT | I=Idle | R=Repair | |
Type | Qty | Hours Worked | Status |
Hilti M/c tool | 01 | ||
Jack hummer | 01 | ||
Drill M/C | 02 | ||
Grinder 4“ | 02 | ||
Grinder 7“ | 03 | ||
Grinder 8“ | 02 | ||
Air Blower | 02 | ||
Welding M/c (PPR) | 03 | ||
Heat Gun (PVC) | 02 | ||
Manual pressure pump | 01 | ||
Jigsaw cutter | 02 | ||
Chawkshaw cutter | 02 | ||
General hand tool box | 10 | ||
3 Ton Pickup / Grader ( 1 /0 ) | 01 | ||
Bus 14 Seater (1) / 34 Seat (1) | 02 | ||
D/c Pickup | 01 | ||
Material Demand | Visitors to site | Sub Contractor’s Equipment | ||||
Item | Unit | Qty | Name of supplier | |||
HDPE PIPES & FITTINGS | VAR | COSMOPLAST. | ||||
PVC CONDUITES & ACCESSORIES | VAR | M.K. | ||||
The contents of this report are a description of items related to the ongoing works or works completed during the day and indicative for the material & manpower on site, and should not in any case be considered a reference document for any contractual implication. |
...