Earned Value Exercise

Question 1

You have just been assigned to take over a project that is already in progress. It is an 18-month project that has been running for 9 months. The project budget is $100,000. According to current work performance information, the project is 60% complete and has cost $80,000 so far.

  1. What is the current Schedule Variance (SV)?

                Scheduled variance = earned value – planned value. == 60000

original Cost = 80,000

(PV) = 100000 *50% = 50,000

(EV) = 60% of 100000 = 60,000

  1. What is the PV for this project at this point in time?

50000

  1. Good News or Bad News?

This is a good news as this scheduled variance is positive, if the sv is positive then the project is in the line of schedule.

Question 2

You have just been assigned to take over a project that is already in progress. It is an 18-month project that has been running for 9 months. The project budget is $100,000. According to current work performance information, the project is 60% complete and has cost $80,000 so far.

  1. What is the current Cost Variance (CV)?

original Cost = 80,000 USD

(PV) = 100000 *50% = 50,000

(EV) = 60% of 100000 = 60,000

 60,000 – 80,000 = - 20,000

  1. What is the EV for this project?

60000

  1. Good News or Bad News?

It is a bad news. Since the cv is negative it is surely a bad news.