PROCESS LAYOUT:

Calculation of Takt

• Takt is the time in which one product should get out of the process irrespective of its total assembly time.

• Calculations

Demand per annum = 30000 Nos product A .

Demand per Month = 30000/12 = 2500 nos

Demand per Day = 2500/25 = 100 Nos

Note: Considered there is 25 Working days in a month

No. of Shift = 1 Shift/Day

Total time Per Shift = 8.5 Hrs / day = 510 min.

Breaks and allowance = 30 min/shift

Available Time per shift = 510-30=480 min / shift

Takt time = Available time/ Demand per shift

Takt Time = 480/100 = 4.8 min per product

Note: The above calculation shows we need to produce 1 product in every 4.8 min, then only we could able to meet daily demand of 100 products.

Calculation of Man Power Requirement and number of station requirement.

Definition: Work content of a product is the total activity involved, in terms of time, to convert raw material into finished goods.

Work content of the Product A is 40 min

Takt of the product A = 4.8 min.

Number of station required = Work content/takt time

= 40 min/4.8 min = 8.33 or 9 stations (Ideally)

Man power required

...