Timberjack Parts Case
Autor: stinkyqf • February 14, 2015 • Case Study • 1,187 Words (5 Pages) • 2,283 Views
1. Describe the steps taken in the software selection process at Timberjack. Compare this to a 'traditional' Systems Development Life Cycle.
Step-1 – intent: A need was realized. In early 1995, the Swedish groups (Sahlqvist and the Marta) were investigating the acquisition of new computer software to run their parts operations. The main reasons where heavy instability of their existing systems. Frequent system failures came from large amounts of modifications of their source code. As a result, they not always rely on the data thorough there present system.
Step-2 – Outlining of a future IS system: Coopers & Lybrand (a management consulting company of about 10,000 employees) helped the top managers outline a future information systems (IS) plan and strategy.
Here are some of ideas included:
• Integration of manufacturing, dealer relationship, sales, parts and service all in one software.
• Hewlett-Packard claimed they would no longer support the current MM3000 software.
• An ERP system or “distribution company package” would best serve parts, and a separate manufacturing system would best suit the factory.
Step-3 – presented to the board: The Coopers & Lybrand consulting firm presented to the board of directors recommendations for the global software strategy. Each organizations were given the task of selecting one system to run the parts side of the organization in the US and Sweden. Utting was assigned to be the project manager.
Step-4 – Software selection consultant: the software selection consultant Bahar Inc. was invited to bid on the software selection contract. A matrix of requirements and definition was created for the us and Swedish groups.
Step-5 – RFP process - software consultant was selected: Timberjack received a quotation from Bahar, the fees would be under $100,000.00 USD which included the following services: RFP creation, vendor and site visits, list of vendors, advice on negotiation of the contract and final selection consulting. Bahar schedules meeting dates to accommodate this list of services. They would work with Coopers & Lybrand to create a requirement list for the project.
Step-6 - RFP process - preliminary lists of requirements: preliminary lists of requirements for the following where created by Bahr with the partnership of Coopers & Lybrand: accounting, finance, purchasing/planning, customer service, pricing, distribution, benefits, information systems, and all capital expenditures.
Step-7- RFP finalized: the RFP with a 52 line item matrix to overview a 200 total page document with over a thousand requirements was developed to guide the software selection, lists of standard reports, and instructions to vendors for the bidding process was included. 50
...