Tutorial 5
Autor: Antonio • June 28, 2012 • Essay • 297 Words (2 Pages) • 1,196 Views
UNIVERSITI TUNKU ABDUL RAHMAN
FACULTY OF ACCOUNTANCY AND MANAGEMENT
ACADEMIC YEAR 2012/2013
BACHELOR OF ACCOUNTING (HONS)
UKAI 2063 ACOUNTING INFORMATION SYSTEMS II
TUTORIAL 5
For each project, you are required to do the following:
• Draw the network diagram for the project and show the critical path.
• Starting all activities as soon as possible, construct a Gantt chart.
• You may also use project management software i.e. MS Project to develop the chart and network diagram.
Project 1
Activity Duration (weeks) Predecessor
A 2 -
B 2 A
C 3 B
D 8 B
E 5 B
F 1 C, D
G 4 D, E
H 5 F, G
I 7 G
J 3 H, I
Project 2
As a project manager for a financial company, you have been asked to conduct user training sessions during the implementation phase for a new information system. You must develop a specific schedule for the tasks (the estimated task duration for each is shown in parentheses):
• First, you need to send an e-mail message to all department managers announcing the training sessions (1 day).
• After the e-mail message
...